• CLADDINGS - WEATHERBOARD

    Normal 0 false false false EN-NZ X-NONE X-NONE MicrosoftInternetExplorer4 ...
  • EXCAVATION

    Excavation commenced on the site in November 2011.  Deep concrete strip and pile footings were dug to bear on solid ground which at times was up to 2m below ground level.  The deep footings and piles were reinforced with steel bars steel from EuroSteel, and poured with insitu...
  • THE FINAL STAGE

    The Owners have now moved into the house.  Landscaping is underway, and finishing touches within the house continue.  Joinery fitments, electrical and sanitary fitments have been installed.  The blog will continue, but with less frequent entries....
  • CLADDINGS - PLY

    The exterior of the rear section of the house has Ecoply® Barrier applied, with the joints between the sheets taped for airtightness. Ecoply® Barrier provides a weather tight rigid air barrier for drained and vented cavity systemsoutside the building frame to effectively replace the traditionally...
  • RAINWATER COLLECTION

    Rainwater is collected from the roof, via spouting / guttering which discharges into vertical downpipes that are run to storage tanks supplied by 'Marley'.  'Marley' diverters to prevent the ingress of debris that may be collected along the way, are fixed to outlets in the downpipe prior to...
  • ROOF FRAMING

    Once the timber framed walls were secured, the timber roof trusses were loaded onto the Laserframe timber framed walls.  The white strip is  the pro clima INTELLO PLUS connection strip applied between the timber framed top plates and the trusses. Steel strip bracing being...
  • CLADDINGS - WEATHERBOARD

    Normal 0 false false false EN-NZ X-NONE X-NONE MicrosoftInternetExplorer4 ...
  • EXCAVATION

    Excavation commenced on the site in November 2011.  Deep concrete strip and pile footings were dug to bear on solid ground which at times was up to 2m below ground level.  The deep footings and piles were reinforced with steel bars steel from EuroSteel, and poured with insitu...
Previous Next

Sunday, July 22, 2012

THE FINAL STAGE

24 comments
The Owners have now moved into the house.  Landscaping is underway, and finishing touches within the house continue.  Joinery fitments, electrical and sanitary fitments have been installed.  The blog will continue, but with less frequent entries.  A professional photographer will provide final photos of the finished Passive House.   There are some items...

Thursday, July 12, 2012

Rainwater is collected from the roof, via spouting / guttering which discharges into vertical downpipes that are run to storage tanks supplied by 'Marley'.  'Marley' diverters to prevent the ingress of debris that may be collected along the way, are fixed to outlets in the downpipe prior to the water reaching its destination - the green storage tanks. ...

HOT WATER

12 comments
Hot water is supplied to the house from an external heat pump, which is strapped to the structure for stability, to meet NZ seismic requirements.   The STIEBEL ELTRON WWK 300A Heat Pump works through utilising the ambient air temperature (thermal energy) and converting this to usable energy to create hot water. A heat pump essentially works in a similar...