FLOOR SLAB - FIRST POUR
The lower level floors of the house are concrete. 'Eurosteel' reinforcing bars connect from the footings, as well as the insitu concrete walls. The insitu concrete floors are poured over 'EXPOL' 100mm thick EPS polystyrene insulation which is laid on top of a continuous layer of...
DRAINAGE
Now that the scaffolding has been removed, machinery can be introduced to the site to dig trenches for service drains around the house. Connections will be made to the local sewer drain, electrical and water provider, and the storm-water will be drained to a collection tank for use on-site....
WIRING
Wiring for the house is being threaded through walls and ceilings to facilitate the needs for each space / room. The wires are taped to the surface they protrude through to ensure airtightness is not compromised.
The wiring boxes are set...
CONCRETE BLOCK WALLS
As well as timber-framed walls being installed, block-layers are building reinforced Firth
concrete-block walls on top of the concrete floor slab. (The concrete block walls are for structural intent rather than a PH consideration in this situation.)
The concrete...
PLASTER BOARD
Gibralter Board ('GIB® Board') is a gypsum and paper board, commonly used to line walls and ceilings. The GIB® range of products can also provide for wet areas, bracing, noise reduction. 'GIB® Board' has been fixed to 'Rondo' galvanised...
WINDOWS
Double-glazed windows are being installed. A presentation was made to a group in which the technology of the window was demonstrated. More on the fabrication of the windows will be added shortly. The following photographs show the 'ProtectoWrap' applied to the window...
FLOOR SLAB - FIRST POUR
The lower level floors of the house are concrete. 'Eurosteel' reinforcing bars connect from the footings, as well as the insitu concrete walls. The insitu concrete floors are poured over 'EXPOL' 100mm thick EPS polystyrene insulation which is laid on top of a continuous layer of...
DRAINAGE
Now that the scaffolding has been removed, machinery can be introduced to the site to dig trenches for service drains around the house. Connections will be made to the local sewer drain, electrical and water provider, and the storm-water will be drained to a collection tank for use on-site....
Previous Next