• CONCRETE WALLS

    The basement walls are ‘EcoBlocks’ filled with concrete, and as the  house is evolves further out of the ground the majority of the wall structure will be constructed of ‘Laserframe’ timber.Steel reinforcing rods forming a forest of bars that protrude from within the polystyrene wall formwork...
  • CONCRETE FLOOR SLAB - SECOND POUR

    In January, the second concrete floor slab was poured for the majority of the house footprint.  Using the same construction as the first floor slab, the insitu concrete floor is poured over 'EXPOL' 100mm thick EPS polystyrene insulation which is laid on top of a continuous layer of polythene....
  • THE FINAL STAGE

    The Owners have now moved into the house.  Landscaping is underway, and finishing touches within the house continue.  Joinery fitments, electrical and sanitary fitments have been installed.  The blog will continue, but with less frequent entries....
  • FOOTING FORMWORK

    As well as providing insulation to separate the concrete structure from the ground (preventing thermal bridging) 'Eco-block' foam insulation creates the formwork for the insitu concrete strip footings, and concrete floor slab edge. 'Eco-block' is an insulated concrete form (ECF) made from expanded...
  • EXCAVATION

    Excavation commenced on the site in November 2011.  Deep concrete strip and pile footings were dug to bear on solid ground which at times was up to 2m below ground level.  The deep footings and piles were reinforced with steel bars steel from EuroSteel, and poured with insitu...
  • FLOOR SLAB - FIRST POUR

    The lower level floors of the house are concrete.  'Eurosteel' reinforcing bars connect from the footings, as well as the insitu concrete walls.  The insitu concrete floors are poured over 'EXPOL' 100mm thick EPS polystyrene insulation which is laid on top of a continuous layer of...
  • CONCRETE WALLS

    The basement walls are ‘EcoBlocks’ filled with concrete, and as the  house is evolves further out of the ground the majority of the wall structure will be constructed of ‘Laserframe’ timber.Steel reinforcing rods forming a forest of bars that protrude from within the polystyrene wall formwork...
  • CONCRETE FLOOR SLAB - SECOND POUR

    In January, the second concrete floor slab was poured for the majority of the house footprint.  Using the same construction as the first floor slab, the insitu concrete floor is poured over 'EXPOL' 100mm thick EPS polystyrene insulation which is laid on top of a continuous layer of polythene....
Previous Next

Friday, April 20, 2012

The Heat Recovery Ventilation System (HRVS) - 'ComfoAir 350' is manufactured by Zehnder (in Germany), imported into New Zealand by Fantech and is distributed by Carters. This is the second house in New Zeland to adopt this system. The 'Fantech' HRVS has been considered throughout the detailing for construction as can be seen in photographic record from the pouring of the concrete floor...

Wednesday, April 4, 2012

INSULATION

12 comments
R4.0 'Pink Batts' fibreglass wool  insulation is placed between the roof framing throughout the house, with straps stapled to the timber framing to secure the blankets in place.strapped into position. Once this layer of insulation is installed, a layer of 'Intello' is fixed and taped to ensure airtightness.  Another layer of r2.2 Fibreglass...

WINDOWS

11 comments
Double-glazed windows are being installed.  A presentation was made to a group in which the technology of the window was demonstrated.  More on the fabrication of the windows will be added shortly.  The following photographs show the 'ProtectoWrap' applied to the window openings prior to the installation of the window frames.  Once the window frames have been installed,...