• RAINWATER COLLECTION

    Rainwater is collected from the roof, via spouting / guttering which discharges into vertical downpipes that are run to storage tanks supplied by 'Marley'.  'Marley' diverters to prevent the ingress of debris that may be collected along the way, are fixed to outlets in the downpipe prior to...
  • CONCRETE FLOOR SLAB - SECOND POUR

    In January, the second concrete floor slab was poured for the majority of the house footprint.  Using the same construction as the first floor slab, the insitu concrete floor is poured over 'EXPOL' 100mm thick EPS polystyrene insulation which is laid on top of a continuous layer of polythene....
  • EXCAVATION

    Excavation commenced on the site in November 2011.  Deep concrete strip and pile footings were dug to bear on solid ground which at times was up to 2m below ground level.  The deep footings and piles were reinforced with steel bars steel from EuroSteel, and poured with insitu...
  • METAL ROOF

    The first section of roof has been laid to the rear section of the PH.  HI RIB trough-section roofing by Steel and Tube has been used, laid over building paper.   Structural steel frames are installed for the roof structure of the front section of the PH....
  • CLADDINGS - PLY

    The exterior of the rear section of the house has Ecoply® Barrier applied, with the joints between the sheets taped for airtightness. Ecoply® Barrier provides a weather tight rigid air barrier for drained and vented cavity systemsoutside the building frame to effectively replace the traditionally...
  • THE FINAL STAGE

    The Owners have now moved into the house.  Landscaping is underway, and finishing touches within the house continue.  Joinery fitments, electrical and sanitary fitments have been installed.  The blog will continue, but with less frequent entries....
  • RAINWATER COLLECTION

    Rainwater is collected from the roof, via spouting / guttering which discharges into vertical downpipes that are run to storage tanks supplied by 'Marley'.  'Marley' diverters to prevent the ingress of debris that may be collected along the way, are fixed to outlets in the downpipe prior to...
  • CONCRETE FLOOR SLAB - SECOND POUR

    In January, the second concrete floor slab was poured for the majority of the house footprint.  Using the same construction as the first floor slab, the insitu concrete floor is poured over 'EXPOL' 100mm thick EPS polystyrene insulation which is laid on top of a continuous layer of polythene....
Previous Next

Wednesday, November 30, 2011

As well as providing insulation to separate the concrete structure from the ground (preventing thermal bridging) 'Eco-block' foam insulation creates the formwork for the insitu concrete strip footings, and concrete floor slab edge. 'Eco-block' is an insulated concrete form (ECF) made from expanded polystyrene (EPS). The black bars are polypropylene connectors that attach to embedded webs. The forms...

Tuesday, November 29, 2011

EXCAVATION

23 comments
Excavation commenced on the site in November 2011.  Deep concrete strip and pile footings were dug to bear on solid ground which at times was up to 2m below ground level.  The deep footings and piles were reinforced with steel bars steel from EuroSteel, and poured with insitu concrete.  Once set, 50mm thick boards of 'Goldfoam' extruded polystyrene (XPS) were laid to insulate...
Insitu concrete was pumped into the Eco-block formwork.  Eco-block is an insulated concrete form (ECF) made from expanded polystyrene (EPS).  The black bars are polypropylene connectors that attach to embedded webs. Concrete was pumped into place,  gently vibrated and the top surface was then trowelled off...